Case Number: | POD2007-00146 |
---|---|
Case Name: | BJ's Wholesale Club |
Review Type: | Original Plan |
Case Description: | BJ's Wholesale Club |
Parcel ID: | 751-744-9528 1320 STARLING DR |
Legal Description: | STARLING DR AC 12.532 84 A1 12 |
Engineer/Applicant: | VHB INC |
Project Case Number: | POD2007-00146 (There are 7 related cases) |
Project Name: | BJ'S WHOLESALE CLUB |
Note: The County of Henrico is not responsible for any information placed in the "Comments" field by the public.
POD2007-00146 - BJ's Wholesale Club - Original Plan
General Menu
Description | Submission Date | Due Date | Completed Date | Status | Reviewer |
---|---|---|---|---|---|
(A010) Application Received | Moffett, Billy | ||||
Comments: -- | |||||
(A025) Enterprise Zone | Welton, Pamela T. | ||||
Comments: part of enterprise zone added 3/18/08 by IT |
POD2007-00146 - BJ's Wholesale Club - Original Plan
Plan Review Menu
Description | Submission Date | Due Date | Completed Date | Status | Reviewer |
---|---|---|---|---|---|
(B005) POD-Original Review Initiated | DONE | Teator, Kate Blakeney | |||
Comments: -- | |||||
(B115) Traffic Engineer Review | CMTS | Jennings, Mike | |||
Comments: PUBLIC WORKS - TRAFFIC ENGINEERING - JENNINGS, MIKE _________ Please see the attached file(s) for more comments: TRA_BJ_s_Wholesale_Club_10AUG07.DOC [Please Note: To view the file(s) you must have the correct software installed. If unable to obtain this, please contact the Reviewer or the Department of Planning for a hard copy of the comments.] | |||||
(B120) DPW Review Engineer | CMTS | Smidler, Sharon S. | |||
Comments: PUBLIC WORKS - REVIEW ENGINEER - SMIDLER, SHARON _________ Please see the attached file(s) for more comments: ENV_BJs_Regency_Square_OWS_10aug07.DOC(DPW - Environmental) ENG_BJ_s_Wholesale_Club_10aug07.DOC(DPW - Engineering) ENV___BJs_Wholesale_Club_at_Regency_Square___10aug07.DOC(DPW - Environmental) [Please Note: To view the file(s) you must have the correct software installed. If unable to obtain this, please contact the Reviewer or the Department of Planning for a hard copy of the comments.] | |||||
(B125) Environ Control Eng Rev | CMTS | Jackson, Scott | |||
Comments: PUBLIC WORKS - ENVIRONMENTAL - JACKSON, SCOTT See the DPW Review Engineer comment section for the Environmental Division comment attachment. | |||||
(B130) Public Utilities Review | CMTS | Morton, Jarad | |||
Comments: DPU - MORTON, JARAD Please see the attached file(s) for more comments: Mark_Williams__BJs_Wholesale_Club_JLM.DOC [Please Note: To view the file(s) you must have the correct software installed. If unable to obtain this, please contact the Reviewer or the Department of Planning for a hard copy of the comments.] | |||||
(B135) Recreation & Parks Review | DONE | Soldano, Mary Ann | |||
Comments: REC & PARKS - SOLDANO, MARY ANN Please see the attached file(s) for more comments: CG83007POD64_07BJWholesale.DOC(POD64-07BJwholesale) [Please Note: To view the file(s) you must have the correct software installed. If unable to obtain this, please contact the Reviewer or the Department of Planning for a hard copy of the comments.] | |||||
(B140) VA Dept of Transport. Review | DONE | Greulich, Anthony | |||
Comments: *Closed by Henrico IT Admin per Tony Greulich in Planning on 12/17/2015 04:46:10 PM* | |||||
(B145) VA Power Review | DONE | Greulich, Anthony | |||
Comments: *Closed by Henrico IT Admin per Tony Greulich in Planning on 05/08/2017 10:56:53 AM* | |||||
(B150) Planning Review | DONE | Goggin, Christina | |||
Comments: PLANNING - GOGGIN, CHRISTINA Additional Comments: Additional Comments for POD-64-07 1. The total building square footage including the mezzanine is 117,286 square feet. Correct site data notes 10B & 12 and all sheets where the building square footage is labeled. Staff will need a revised plan accommodating the required parking for the September Planning Commission hearing. 2. For site data note 10A, staff calculates that 587 spaces are required. The site is short 13 spaces. ). How these spaces will be provided? The proposed building could be reduced 2,600 sqft or the fueling center could be reduced in size to provide area for the required parking. 3. Move the cart corrals from underneath the landscape islands in front of the store so they are better distributed within customer parking. 4. Is the cross walk at the main entrance the only 1 proposed. Provide more crossings across the main drive aisle. 5. Staff cannot locate the tree protection details on sheet 5.01. Use orange construction safety fence due the extreme sensitivity of the proffered buffer. 6. Staff cannot locate the 6? screen wall detail along the northern and eastern property lines. These screening sections will need to be connected to each other for a comprehensive fence line. 7. Staff recommends a fence or block wall min 6? in height along the residential zoned property. The fence should be installed 10? from the curb line so it is located near the top of the finished grades but still provides area for landscaping on the retail side. 8. Has BJ?s and Quioccasin Church talked about access so the church could utilize BJ?s employee parking for overflow when the store isn?t open? There will need to be a sidewalk and gate in the fence is that is implemented. 9. Label the northern most parking lot as employee parking. 10. Staff recommends moving the propane tank closer to the store?s entrance to create an additional landscape island. Also, provide the chain link fence detail within the plan with height info. Staff recommends black vinyl chain link vs. silver. 11. Is the painted strip south of the gas pumps 4? or 4?? Plan states 4?. This area should be raised curb and gutter so landscaping can be installed to provide screening and traffic channelization. 12. Provide the screening details for all transformers and generators. 13. Signage is not part of this approval. Only 1 free standing sign will be permitted on site. 14. Additional comments may be forthcoming a revised plan submission. Architectural plan review 1. The proposed buildings need additional architectural details to break up the buildings? mass. These can include pilasters, varying the parapet decorative brick patterns such as solider courses or recessed sections that create a pilaster. Provide revised architecturals that address staff?s concerns prior to the public hearing. 2. The fuel canopy columns should be constructed out of brick to match the buildings. Landscape plan review 3. Staff has not had an opportunity to review the schematic landscape plan. 4. The landscape plan will need to be removed from the signature submittal. | |||||
(B155) Education Review | DONE | Greulich, Anthony | |||
Comments: Activity completed to close out case | |||||
(B30) Building Insp Rev | APPR | Gordon, Richard T | |||
Comments: -- | |||||
(B40) Fire Review | APPR | Rastegar, Abdol Russell | |||
Comments: FIRE - RASTEGAR, RUSSELL | |||||
(B70) Police Review | CMTS | Vann, Kimberly | |||
Comments: POLICE - VANN, KIMBERLY Please see the attached file(s) for more comments: BJ_s_Wholesale.DOC [Please Note: To view the file(s) you must have the correct software installed. If unable to obtain this, please contact the Reviewer or the Department of Planning for a hard copy of the comments.] |
POD2007-00146 - BJ's Wholesale Club - Original Plan
FCP - Original Sub
Description | Submission Date | Due Date | Completed Date | Status | Reviewer |
---|---|---|---|---|---|
(D003) Orig Submission-FCP-Initiated | DONE | Welton, Pamela T. | |||
Comments: -- | |||||
(D115) Traffic Engineer Review - FCP | CMTS | Jennings, Mike | |||
Comments: PUBLIC WORKS - TRAFFIC ENGINEERING - JENNINGS, MIKE will be attached to review engineer comments | |||||
(D120) DPW Review Engineer - FCP | CMTS | Smidler, Sharon S. | |||
Comments: PUBLIC WORKS - REVIEW ENGINEER - SMIDLER, SHARON _________ Please see the attached file(s) for more comments: TRA_BJ_s_Wholesale_Club_12OCT07.DOC(DPW Traffic) ENV___BJs_Wholesale_Club_at_Regency_Square___12oct07.DOC(DPW Environmental) ENG_BJ_s_Wholesale_Club_12oct07.DOC(DPW Engineering) [Please Note: To view the file(s) you must have the correct software installed. If unable to obtain this, please contact the Reviewer or the Department of Planning for a hard copy of the comments.] | |||||
(D125) Environ Control Eng Rev - FCP | CMTS | Jackson, Scott | |||
Comments: PUBLIC WORKS - ENVIRONMENTAL - JACKSON, SCOTT See the DPW Review Engineer comment section for the Environmental Division comment attachment. | |||||
(D130) Public Utilities Review - FCP | CMTS | Clark, John | |||
Comments: DPU - CLARK, JOHN Please see the attached file(s) for more comments: BJ_Wholesale_Club_2nd_review_11_02_07.DOC [Please Note: To view the file(s) you must have the correct software installed. If unable to obtain this, please contact the Reviewer or the Department of Planning for a hard copy of the comments.] | |||||
(D150) Planning Review - FCP | DONE | Goggin, Christina | |||
Comments: PLANNING - GOGGIN, CHRISTINA Additional Comments: October 31, 2007 Randall R. Silber Director of Planning (804) 501-4602 Mr. Jon P. Carty, P.E. VHB 115 South 15th Street, Suite 200 Richmond, VA 23219-4209 RE: POD 64-07 BJ?s Wholesale Center Construction Plan Review Dear Mr. Carty: The Planning Department has completed its review of the referenced plans submitted October 11, 2007 and has the following comments: 1. Correct site data notes 10, 12 & 14 to correspond with the revised building area. 2. Correct site data note 10 to account for the mezzanine and additional parking. 3. Correct site data note 12A to account for the mezzanine. 4. For site data note 13, staff calculates the gross site is 545,807 sqft. 5. On Sheet 2.01, correct the following items in the zoning summary chart: a. There is no minimum lot width for retail in B-2. b. There is no maximum limit of building stories, just building height. c. A 40? rear yard is required against ?R? zoning. 6. The concrete 4? islands to the north and south of the fueling center should be redesigned as landscape strips for ornamental trees and shrubs. 7. Continue the sidewalk along Starling Dr. to the southernmost property line. 8. Show the sidewalk/access between the northern most parking lot to the church. 9. Move the cart spaces in the northern most parking lot so they are not adjacent to landscape islands. The carts can be moved in a couple of spaces. 10. Remove the existing space overlay west of the Wellness Center from the layout plan. 11. The concrete island adjacent to the propane tanks should be redesigned as landscape a landscape island. 12. On sheet 5.01, provide the tree protection symbol in the legend and reference sheet 6.02 for the details. 13. Staff cannot locate the dumpster screening details or other items proposed to be screened within the plan. Dumpster screening needs to be 8? tall with opaque gates. 14. Detail sheet 6.04 shows the chain link detail including color. Add a note to that detail indicating that the fence will by black vinyl. Staff recommends that the developer consider utilizing a decorative aluminum fence instead. Could the rear and side be constructed out of block to match the building? 15. Provide a note on the plan that the retaining wall be constructed with block that matches the building. 16. Provide the location and method of screening for all HVAC/mech equipment including transformers. If the equipment is intended to be on the ground, show location and screening method. Staff recommends that is constructed of finished architectural block to match the buildings. 17. Scan in and include the POD approval letter in future submissions. 18. Remove the landscape plans from future submittals or print across both pages and cover sheet that the landscaping is not part of this review and approval. 19. Additional comments pending comments from Public Utilities. Please address these comments and the comments from the other agencies and submit 7 sets of construction plans for review. Should you have any questions, please contact me at 501-5159. Sincerely, Christina L. Goggin, AICP County Planner P.c. Chris Heaphy ? The Taubman Company Peter Hopley ? BJ?s Wholesale Club, Inc. | |||||
(D30) Building Insp Review - FCP | APPR | Gordon, Richard T | |||
Comments: -- | |||||
(D40) Fire Review - FCP | APPR | Rastegar, Abdol Russell | |||
Comments: FIRE - RASTEGAR, RUSSELL |