Case Number: | POD2022-00220 |
---|---|
Case Name: | QTS East - Phase 2 |
Review Type: | Construction Plan |
Case Description: | QTS East - Phase 2 |
Parcel ID: | 847-703-4371 6000 TECHNOLOGY BLVD |
Legal Description: | ELKO ROAD AC PAR 1 (PARCEL 3) 58 A1 2 |
Engineer/Applicant: | TOWNES SITE ENGINEERING |
Master Case: | POD2022-00169 |
Project Case Number: | POD2022-00169 (There are 4 related cases) |
Project Name: | WHITE OAK SEMICONDUCTOR |
Note: The County of Henrico is not responsible for any information placed in the "Comments" field by the public.
Description | Submission Date | Due Date | Completed Date | Status | Reviewer |
---|---|---|---|---|---|
(2120) DPW - Design Review | CMTS | Gruendl, Alexandria D. | |||
Comments: PUBLIC WORKS - REVIEW ENGINEER - GRUENDL, ALEXANDRIA D. _________ Please see the attached file(s) for more comments: TRA_QTS_East___Phase_2_POD_23JUN22.DOCX ENV___QTS_East___Phase_II___16jun22.DOC CON_QTS_East___Ph__2___22__June_2022___.DOCX [Please Note: To view the file(s) you must have the correct software installed. If unable to obtain this, please contact the Reviewer or the Department of Planning for a hard copy of the comments.] Additional file(s): ENG - QTS EAST EXPANSION - PH 2 - WET POND - 16JUN22.DOCX ENG - QTS EAST EXPANSION - PHASE 2 - 16JUN22.DOCX |
*This site contains Comments made after February 1, 2007
If you would like to view comments prior to Feb 1 2007, please contact the Planning Department at 804-501-4602.